A United Kingdom supplier, with 4 awarded contracts, totalling £55.0m, most recently 3 months ago.
This contract involves the reconstruction of the 330 kV single-circuit overhead power line from Jurbarkas to Bitėnai into a double-circuit line. The first phase of the work must be completed by January 7, 2022, and the second phase must be finished, with the project fully implemented, by April 1, 20
This contract involves the reconstruction of the 330 kV single-circuit overhead line from Klaipėda to Grobinė into a double-circuit line. The work is divided into two phases: Phase I must be completed by January 7, 2022, and Phase II, along with the overall project implementation, must be finished b