This contract involves the design of a 110 kV substation named 'Beshovitsa' to connect the solar power plant 'Elidis Solar' and the associated electrical network, owned by 'ESP Elidis Solar Park' LLC. The contract also includes author supervision during the construction phase.
This contract involves the execution of author supervision and, if necessary, the execution of geodetic surveys and the preparation of executive documentation for the project "Construction of a sewer system for the "Septemvriitsi" 110/20 kV substation." The project aims to ensure proper infrastructu
This contract involves the preparation of a detailed development plan for the project site 'Madara 2' (400/110 kV) located in Shumen, Bulgaria. The specific site has an identifier of 83510.147.16 and covers an area of 458,869 m², designated primarily for forest use. This project is part of the inves