This contract involves the modernization of the 110/15 kV RPZ-9 Białystok substation, operated by PGE Dystrybucja S.A. in Białystok. Suppliers are required to refer to Annex 1 and 1.1 of the procurement documents for detailed specifications. The contractor or subcontractor must employ workers under
Tender closed on 12 Dec 2025. Awaiting award.
Only 2 prior awards here — too little to read.
In construction, PGE DISTRIBUTION SA has awarded 2 contracts to 2 suppliers.
Across construction, the most active winners are HOLCIM UK LIMITED, TARMAC TRADING LIMITED, LINDUM GROUP LIMITED — the field to beat, or your route in as a partner.
PGE Dystrybucja S.A. is seeking suppliers for the delivery of high voltage switches in 2027. This contract includes detailed specifications outlined in the procurement documents, particularly in Annex 1 of the Terms of Reference. Suppliers are encouraged to review these documents to understand the r
This contract involves the construction and modernization of medium voltage power lines in the Sokółka and Krynki areas, managed by PGE Dystrybucja S.A. The detailed specifications can be found in Attachments 1 and 1.1 of the procurement documents. The contractor or subcontractor must employ workers
This contract involves the purchase and installation of two transformers with a voltage of 110/15 kV and a target capacity of 40 MVA for the Tomaszów 1 substation. Suppliers are invited to submit proposals for the provision of these electrical equipment and installation services. The deadline for su
This contract involves establishing a framework agreement for the development of the Central Measurement Data Repository system over a period of three years. The procurement process is conducted in accordance with the Public Procurement Law, specifically through a negotiated procedure based on Artic
Stotfold Town Council seeks experienced contractors to renovate the cemetery toilet block, adding compliant facilities, solar heating, and storage within a £190,000-£210,000 budget.
Construction of an adapted ground floor cloakroom and WC facility for a vulnerable tenant at a Blyth residential property, scheduled to begin November 2026 over 14 weeks.
Design-and-build glazed envelope and structural steelwork renewal for the Grade II listed Barbican Arts Centre, including new glazing systems, steel framing, and façade access solutions across multiple building sections.
EKFB requires a subcontractor for trial installation of access stairs and hard landscaping at Claydon Road Overbridge, with potential for future phases if successful.