    ContractsConstruction Works for Power Plants – Moabit Coal Phase-Out (MoKA) Lot 2: Structural Renovation of the Listed Boiler House 2 for the Installation of Three New Hot Water Generation Systems
    Awarded contract

    Construction Works for Power Plants – Moabit Coal Phase-Out (MoKA) Lot 2: Structural Renovation of the Listed Boiler House 2 for the Installation of Three New Hot Water Generation Systems

    Status
    Awarded
    Published 7 Aug 2025

    This project involves the construction of gas-fired district heating generation plants at the Reuter West and Moabit sites to replace coal-fired facilities, facilitating Berlin's coal phase-out by the end of 2029. At Reuter West, a 4-boiler system with a total production capacity of 160 MWth will be

    🇩🇪GermanyPublished 7 Aug 2025· 1 years agoviaTED
    Status
    Awarded
    Published 7 Aug 2025

    Decision brief

    4 fields
    • Contract value
      Not disclosed
      Source did not declare a figure
    • Closing date
      Rolling
      No closing date published
    • Sector
      Construction
      Browse related listings
    • Location
      🇩🇪Germany

    Suppliers

    1 supplier
    • HP
      HELMUT PETERS CONSTRUCTION COMPANY LTD
    Lead contractor

    Lifecycle

    Awarded

    Contract awarded. Originally published 1 years ago.

    7 August 2025
    Awarded — no open tender advertised

    Brief

    This project involves the construction of gas-fired district heating generation plants at the Reuter West and Moabit sites to replace coal-fired facilities, facilitating Berlin's coal phase-out by the end of 2029. At Reuter West, a 4-boiler system with a total production capacity of 160 MWth will be built, and at Moabit, a 3-boiler system with a total production capacity of 120 MWth will be established. This opportunity focuses on Lot 2, which includes structural renovation work on the listed Boiler House 2 to accommodate three new hot water generation systems and associated auxiliary buildings at the Moabit site. The contractor must perform preparatory work in the existing Boiler House, ensuring that operations of existing facilities continue until the new systems are operational. The completion of construction work is planned for Q3/2026, with the commissioning of the new system (Lot 1, not included in this announcement) scheduled for Q1/2027. Special requirements must be met due to the need to maintain existing operations and the constraints of the urban environment and heritage protection. Key tasks include vibration-sensitive demolition of approximately 400 m³ of concrete slabs and foundations, around 350 m³ of earthworks, specialized deep foundation work (micropiles), approximately 750 m³ of reinforced concrete work for foundations and slabs, and scaffold construction, as well as about 50 tons of steel construction work for a pipe bridge. All work must be carried out in a confined existing environment.

    Track record

    2 awards · 2 winners
    Thin record

    Only 2 prior awards here — too little to read.

    In construction, BEW BERLIN ENERGY AND HEAT LTD has awarded 2 contracts to 2 suppliers.

    Who wins here
    1. HELMUT PETERS CONSTRUCTION COMPANY LTD1× · 50%
    2. DSD POWER TECHNOLOGIES GMBH1× · 50%

    Across construction, the most active winners are HOLCIM UK LIMITED, TARMAC TRADING LIMITED, LINDUM GROUP LIMITED — the field to beat, or your route in as a partner.

    More from BEW BERLIN ENERGY AND HEAT LTD

    1 listingView all →
    AwardedConstruction🇩🇪Germany

    Construction of Gas-Fired Boiler Systems in Berlin

    This contract involves the planning, delivery, and installation of three gas-fired boiler systems, each with a capacity of 40 MW, at the HKW Moabit site in Berlin. This project, known as 'MoKA', aims to support the transition away from coal in the region. Suppliers are invited to participate in this

    BEW BERLIN ENERGY AND HEAT LTD
    Published 7 Aug 2025

    Open in Construction

    4 open listingsView all →
    Construction🇮🇪Ireland

    Enniscrone Coastal Development Project – New Community Pavilion, Bath House Refurbishment, and Public Realm Enhancement

    Major coastal regeneration project in Enniscrone, Ireland featuring a new community pavilion, refurbished bath house, and extensive public realm improvements with accessibility enhancements.

    est.€7,000,000SLIGO COUNTY COUNCIL
    Published 21 Sept 2026
    Construction🇮🇪Ireland

    Pedestrian Footpath Construction at Irish National War Memorial Gardens, Dublin

    Construction of new pedestrian footpaths and associated works at the Irish National War Memorial Gardens in Dublin.

    €1nominalOFFICE OF PUBLIC WORKS OPW
    Published 21 Sept 2026
    Construction🇮🇪Ireland

    Steel Footbridge Construction Over Owenriff River in Oughterard, Ireland

    Construction tender for a new steel footbridge with associated civil works over the Owenriff River on Ireland's N59 near Oughterard.

    est.€2,200,000GALWAY COUNTY COUNCIL
    Published 21 Sept 2026
    Construction🇮🇪Ireland

    Wooden Boardwalk Removal and Replacement Project in Scragh Bog, Ireland

    Reconstruction of a 250-metre FSC Douglas Fir boardwalk at Scragh Bog, Ireland, including removal of existing structure, installation of crossings and passing points, and placement of benches.

    est.€250,000DEPARTMENT OF HOUSING LOCAL GOVERNMENT AND HERITAGE
    Published 21 Sept 2026
    Take action
    View on sourceTED

    Award notice and full record on the publisher's site

    Publisher
    Publications Office of the European Union
    Licence
    EU 2011/833/EU + TED reuse notice
    Source
    ted.europa.eu
    Record ID
    522084-2025
    BB
    Buyer
    BEW BERLIN ENERGY AND HEAT LTD
    Sector
    Construction